Active incidents...
maintenance
scheduled
started Tue, Nov 24, 2026, 06:00 UTC
BEZEQINT (ISP), BEZEQINT-NG (ISP), DARKFIBER 2 (ISP), VM CLUSTER, core switch l3 - ar-sh7280-1, core switch l3 - ar-sh7280-2, Nyon (ISP)
Dear Customer,
Please be advised of a planned maintenance activity at the Shacham Tech Data Center.
Maintenance Details
Reference Number: PW-52336 and 52337
Location: Shacham 40, Petach Tikva
Start Time: 24-Nov-2026 06:00-15:00 (UTC)
End Time: 25-Nov-2026 06:00-15:00 (UTC)
MOP: Yearly maintenance of Schneider Electric UPS units supporting Shacham 40 Datacenter
Visual inspection and Battery testing, cleaning, bolt tightening, etc.
Expected Service Impact: No impact is anticipated.
Customer Action Required: No customer action is required.
Risk Assessment: In the event of IEC (main public grid) Blackout, 1 of 3 UPS arrays undergoing Maintenance will not be available.
The Arrays will be maintained sequentially.
Nov. 24: Power Leg A will be maintained and not backed up by UPS.
Nov. 25: Power Leg B will be maintained and not backed up by UPS.
Always at your service, Interhost.
maintenance
scheduled
started Tue, Nov 24, 2026, 06:00 UTC
BEZEQINT (ISP), BEZEQINT-NG (ISP), DARKFIBER 2 (ISP), VM CLUSTER, core switch l3 - ar-sh7280-1, core switch l3 - ar-sh7280-2, Nyon (ISP)
Dear Customer,
Please be advised of a planned maintenance activity at the acham Tech Data Center.
Maintenance Details
Reference Number: PW-52361
Location: Shacham 40, Petach Tikva
Start Time: 24/11/2026 06:00 (UTC)
End Time: 24/11/2026 15:00 (UTC)
Assets being maintained: Replacement of 2 EOL Inrow Units
MOP: The replacement of two INROW units at stage A shaham 40 datacenter.
Expected Service Impact: No impact is anticipated.
Customer Action Required: No customer action is required
Risk Assessment: No risk is expected.
Always at your service, Interhost.
maintenance
scheduled
started Sun, Nov 22, 2026, 06:00 UTC
BEZEQINT (ISP), BEZEQINT-NG (ISP), DARKFIBER 2 (ISP), VM CLUSTER, core switch l3 - ar-sh7280-1, core switch l3 - ar-sh7280-2, Nyon (ISP)
Dear Customer,
Please be advised of a planned maintenance activity at the Shacham Tech Data Center.
Maintenance Details:
Reference Number: PW-52306 and 52307
Location: Shacham 40, Petach Tikva
Start Time: 22-Nov-2026 06:00 (UTC)
End Time: 23-Nov -2026 17:00 (UTC)
MOP:
Yearly maintenance of UPS units supporting Shacham 40 and Sivim 18 Datacenters
Visual inspection and Battery testing, cleaning, bolt tightening, etc.
Expected Service Impact: No impact is anticipated.
Customer Action Required: No customer action is required.
Risk Assessment: In the event of IEC (main public grid) Blackout, UPS undergoing Maintenance will not be available.
Nov. 22: Power Leg A will be maintained and not backed up by UPS.
Nov. 23: Power Leg B will be maintained and not backed up by UPS.
Always at your service, Interhost.
maintenance
scheduled
started Tue, Nov 17, 2026, 04:00 UTC
BEZEQINT (ISP), BEZEQINT-NG (ISP), DARKFIBER 2 (ISP), VM CLUSTER, core switch l3 - ar-sh7280-1, core switch l3 - ar-sh7280-2, Nyon (ISP)
Dear Customer,
Please be advised of a planned maintenance activity at the Shacham Tech Data Center.
Maintenance Details
Reference Number: PW-52343
Location: Shacham 40, Petach Tikva
Start Time: 17-Nov-2026 04:00 (UTC)
End Time: 18-Nov-2026 15:00 (UTC)
Asset(s) being maintained: Replacement of a 2000 Litre Generator Fuel tank.
MOP: Removal of old Tank and loading the new Tank to the rooftop.
Disconnecting and reconnecting Fuel lines.
Fuel Refill\Transfer from old Tank.
Expected Service Impact: No impact is anticipated.
Customer Action Required: No customer action is required.
Risk Assessment: A single Generator (at a time) will not be available for approx. 90 minutes while being replaced.
Always at your service, Interhost.
maintenance
scheduled
started Sun, Nov 15, 2026, 06:00 UTC
BEZEQINT (ISP), BEZEQINT-NG (ISP), DARKFIBER 2 (ISP), VM CLUSTER, core switch l3 - ar-sh7280-1, core switch l3 - ar-sh7280-2, Nyon (ISP)
Dear Customer,
Please be advised of a planned maintenance activity at the Shacham Tech Data Center.
Reference Number: PW-52165
Location: Shacham 40, Petach Tikva
Start Time: 15-Nov-2026 06:00 (UTC)
End Time: 30- Nov-2026 14:00 (UTC)
Scope of Work: Semi-Annual Preventive Maintenance of Rooftop Cooling Systems
Expected Service Impact: No interruption to customer services is anticipated. During the maintenance window, preventive maintenance activities will be performed on multiple cooling systems and related sub-systems.
Risk Assessment: A temporary increase in environmental temperatures may occur during the maintenance activities; however, all efforts will be made to minimize any impact.
Always at your service, Interhost.
Upcoming maintenance...
Scheduled
Starts Sun, Nov 29, 2026, 24:00 UTC — Ends Sun, Nov 29, 2026, 04:00 UTC · TAMARES TELECOM (ISP)
General Information
Activity Performer : 3rd Party Provider
Activity Description : Emergency Mandatory Software Upgrade
Activity Number :
TPW#509469
Activity Details
Activity Date : 29.11.2026 GMT
Activity Start : 29.11.2026 00:00 GMT ( Local 29.11.2026 02:00 IST )
Activity End : 29.11.2026 04:00 GMT ( Local 29.11.2026 06:00 IST )
Affected Services
INH-E10-002
Downtime : 240 Minutes
Scheduled
Starts Mon, Dec 7, 2026, 20:00 UTC — Ends Tue, Dec 8, 2026, 04:00 UTC · BEZEQINT (ISP), BEZEQINT-NG (ISP), DARKFIBER 2 (ISP), VM CLUSTER, core switch l3 - ar-sh7280-1, core switch l3 - ar-sh7280-2, Nyon (ISP)
Dear Customer,
Please be advised of a planned maintenance activity at the Shacham Tech Data Center.
Maintenance Details
Reference Number: PW-52023
Location: Shacham 40, Petach Tikva
Start Time: 07-Dec-2026 20:00 (UTC)
End Time: 08-Dec-2026 04:00 (UTC)
Assets being maintained: High Voltage Systems, Transformers, Mains, Emergency stoppers
MOP: As part of the maintenance procedure, the facility will transition from IEC utility power to generator power and will return to IEC utility power once the maintenance has been successfully completed.
Expected Service Impact: No impact is anticipated.
Customer Action Required: No customer action is required.
Risk Assessment: Low risk of power loss on one of 2 if a Generator fails. Returning to IEC power will take 15 minutes on the Power Leg affected.
Always at your service, Interhost.