Complete
The maintenance is now complete. Thanks for your patience.
sorryapp-import · 2025-11-24 15:00:07 UTC
Underway
The scheduled maintenance is now underway. We'll keep you updated on our progress.
sorryapp-import · 2025-11-24 06:00:00 UTC
Scheduled
Dear Customer,
We would like to inform you about a planned work scheduled in Shacham Tech Data Center.
PW Reference Number: 48441
Locations: Shacham 40 Petach Tikva & Sivim 18 Petach Tikva Data Centers.
Maintenance Window:
Start date/time: 24-11-2025 06:00 UTC
End date /time: 24-11-2025 15:00 UTC
Scope of work: Annual Maintenance of Aviem UPS Systems for Leg B.
Impact: No Downtime expected
During the Maintenance 1 of 2 Power Legs will be removed from the UPS. Generators Backup will be active.
If you have any further inquiries regarding this work, please do not hesitate to contact us.
Always at your service, Interhost.