Planned Maintenance at Shacham Data Center

Wed, Dec 24, 2025, 21:00 UTC — Thu, Dec 25, 2025, 02:00 UTC · 5 hours

Resolved

Complete

The maintenance is now complete. Thanks for your patience.

sorryapp-import · 2025-12-25 02:00:02 UTC

Underway

The scheduled maintenance is now underway. We'll keep you updated on our progress.

sorryapp-import · 2025-12-24 21:00:02 UTC

Scheduled

Dear Customer,
We would like to inform you about a planned work scheduled in Shacham Tech Data Center.

PW Reference Number: 48732
Location: Shacham 40 Petach Tikva

Maintenance Window:
Start date/time: 24-12-2025 21:00 UTC
End date /time: 25-12-2025 02:00 UTC

Scope of work: High Voltage Transformer's termination lug replacement.

Impact: No downtime expected

MOP: Replacement of a worn termination lug feeding the transformer.

During the Maintenance the power to the facility will be supplied by the Generators.
If you have any further inquiries regarding this work, please do not hesitate to contact us.

Always at your service, Interhost.

sorryapp-import · 2025-12-11 15:05:04 UTC