Planned Maintenance at Shacham Data Center

Sun, Jan 18, 2026, 22:00 UTC — Mon, Jan 19, 2026, 24:00 UTC · 2 hours

Resolved

Complete

The maintenance is now complete. Thanks for your patience.

sorryapp-import · 2026-01-19 00:00:00 UTC

Underway

The scheduled maintenance is now underway. We'll keep you updated on our progress.

sorryapp-import · 2026-01-18 22:00:05 UTC

Scheduled

Dear Customer,
We would like to inform you about a planned scheduled work at the Shacham Tech Data Center.

PW Reference Number: 48906
Location: Shaham 40 Petach Tikva Data Center

Maintenance Window:
Start Date/Time: 18-01-2026 22:00 (UTC)
End Date/Time: 19-01-2026 00:00 (UTC)

Scope of Work: Reseating Module #1 in Router #1.

Impact: None.

MOP: Removal of module number 1 from the router for 60 seconds and re-insertion back.

Note: All systems and connectivity will remain fully operational throughout the maintenance.

If you have any further inquiries regarding this work, please do not hesitate to contact us.

Always at your service, Interhost