Planned Maintenance at Shacham Data Center

Sun, Feb 15, 2026, 05:00 UTC — Tue, Feb 17, 2026, 13:00 UTC · 2d 8h

Resolved

Complete

The maintenance is now complete. Thanks for your patience.

sorryapp-import · 2026-02-17 13:00:00 UTC

Underway

The scheduled maintenance is now underway. We'll keep you updated on our progress.

sorryapp-import · 2026-02-15 05:00:05 UTC

Scheduled

Dear Customer,

We would like to inform you about a planned work scheduled in Shacham Tech Data Center.

PW Reference Number: 49146
Location: Shaham 40 Petach Tikva. Data Center.

Maintenance Window:
Start date/time: 15-02-2026 05:00 UTC
End date /time: 17-02-2026 13:00 UTC

Scope of work: Periodic inspection for all generators at the facility.

Impact: No impact is expected

MOP: The maintenance will include a visual inspection of the generators and their operational testing.

Always at your service, Interhost.