Planned Maintenance at Shacham Data Center

Sun, Feb 22, 2026, 05:00 UTC — Wed, Feb 25, 2026, 13:00 UTC · 3d 8h

Resolved

Complete

The maintenance is now complete. Thanks for your patience.

sorryapp-import · 2026-02-25 13:00:03 UTC

Underway

The scheduled maintenance is now underway. We'll keep you updated on our progress.

sorryapp-import · 2026-02-22 05:00:03 UTC

Scheduled

Dear Customer,
We would like to inform you about a planned work scheduled in Shacham Tech Data Center.

PW Reference Number: 49125
Location: Shaham 40 Petach Tikva. Data Center, Data Hall -A

Maintenance Window:
Start date/time: 22-02-2026 05:00 UTC
End date /time: 25-02-2026 13:00 UTC

Scope of work: Mapping and testing grounding power supply connections

Impact: No impact is expected

MOP: Mapping and testing grounding power supply. under the raised floor, including connection repairs.

If you have any further inquiries regarding this work, please do not hesitate to contact us.

Always at your service, Interhost.