Dear Customer,
We would like to inform you about a planned work scheduled in Shacham Tech Data Center.
PW Reference Number: 50317
Location: Shaham 40 Petach Tikva. Data Center, Data Hall -A
Maintenance Window:
Start date/time: 15-04-2026 11:00 PM GMT+3
End date /time: 16-04-2026 05:00 PM GMT+3
Scope of work: Mechanical bypass system Installation for the Phase B power supply
Impact: No impact is expected
MOP: Maintenance will be performed on one power feed at a time. During the work window, only one power feed will remain active