Complete
The maintenance is now complete. Thanks for your patience.
sorryapp-import · 2026-03-25 14:00:00 UTC
Underway
The scheduled maintenance is now underway. We'll keep you updated on our progress.
sorryapp-import · 2026-03-22 06:00:00 UTC
Scheduled
Dear Customer,
We would like to inform you about a planned work scheduled at Shacham Tech Data Center.
PW Reference Number: 50386
Location: Shaham 40 Petach Tikva. Data Center, Data Hall -A,B
Maintenance Window:
Start date/time: 25-03-2026 06:00 AM UTC
End date /time: 25-03-2026 14:00 PM UTC
Scope of work: Schneider Electric 1500KVA UPS systems Inspection
Impact: No impact is expected
MOP: The maintenance will include inspections and measurements. No battery discharge testing will be performed.
If you have any further inquiries regarding this work, please do not hesitate to contact us.
Always at your service, Interhost.
sorryapp-import · 2026-03-19 07:22:46 UTC