Planned Maintenance at Shacham Data Center

Mon, Oct 19, 2026, 20:00 UTC — Tue, Oct 20, 2026, 03:00 UTC · 7 hours

Complete

Complete

Maintenance complete

ariel · 2026-10-20 14:30:50 UTC

Complete

Maintenance complete

ariel · 2026-10-20 14:30:50 UTC

Scheduled

Dear Customer,
Please be advised of a planned maintenance activity at the Shacham Tech Data Center.

Maintenance Details:

Reference Number: PW-52022
Location: Shacham 40, Petach Tikva
Start Time: 19-Oct-2026 20:00 (UTC)
End Time: 20-Oct-2026 03:00 (UTC)

Scope of Work: Replacement of the cooling system serving Generator 3.
The existing modular cooling unit will be removed and replaced with a new system.

Expected Service Impact: No interruption to customer services is expected.
During the maintenance window, Generator 3 will be unavailable to provide backup power to the Israel Electric Company (IEC) feed.
The facility's UPS infrastructure will continue to support the affected power path for approximately 20 minutes in the event of an IEC outage.

Should an IEC power outage exceed UPS autonomy during the maintenance window:

One of the facility's two power feeds may become unavailable.
Equipment connected to a single power feed may experience service interruption or shutdown.
Equipment with dual independent power feeds is not expected to be affected.
Customer Action Required

No customer action is required.

Customers operating single-fed equipment should be aware of the elevated risk associated with an extended IEC outage during the maintenance window.

Always at your service, Interhost.

ariel · 2026-10-13 13:27:06 UTC