Planned Maintenance at Shacham Data Center

Wed, Sep 23, 2026, 05:00 UTC — Wed, Sep 23, 2026, 13:00 UTC · 8 hours

Scheduled

Scheduled

Dear Customer,

We would like to inform you about a planned work scheduled in Shacham Tech Data Center.

PW Reference Number: 51732

Location: Shacham 40 Petach Tikva

Maintenance Window:
Start date/time: 23-09-2026 05:00 UTC
End date /time: 23-09-2026 13:00 UTC

Scope of work: Audit of KVA1500 UPS Systems.
Impact: No downtime expected

MOP: Battery testing and UPS Data reports.
During the Maintenance 1 of 2 Power Legs will be removed from the UPS. Generators Backup will be active.

If you have any further inquiries regarding this work, please do not hesitate to contact us.

Always at your service, Interhost.

ariel · 2026-09-10 10:37:26 UTC