Planned Maintenance at Shacham Data Center

Sun, Aug 16, 2026, 18:00 UTC — Sun, Aug 16, 2026, 20:00 UTC · 2 hours

Complete

Complete

Maintenance 51447 Completed

ariel · 2026-08-18 07:29:50 UTC

Complete

Maintenance 51447 Completed

ariel · 2026-08-18 07:29:50 UTC

Scheduled

Dear Customer,

We would like to update you about a new Date for a planned work scheduled in Shacham Tech Data Center.

PW Reference Number: 51447

Location: Shacham 40 Petach Tikva

Maintenance Window:
Start date/time: 16-08-2026 06:00 UTC
End date /time: 16-08-2026 18:00 UTC

Scope of work: Replacement of Chiller's Relay Units.

Impact: No downtime expected.

MOP: Inactive Chiller's Relay Unit will be replaced, then Inactive Chiller will be activated, then Secondary Chiller will be maintained.

If you have any further inquiries regarding this work, please do not hesitate to contact us.

Always at your service, Interhost.

ariel · 2026-08-06 09:02:01 UTC